|
Crystal Rig Wind Farm is an operational onshore wind farm located on the Lammermuir Hills in the Scottish Borders region of Scotland. When phase 1 was completed in May 2004 it was the largest wind farm in Scotland. As a result of 3 extensions it is currently the 2nd largest wind farm in the UK, in terms of nameplate capacity and one of the top five largest in number of turbines. The wind farm was developed and is owned by Fred. Olsen Renewables Ltd. part of the Fred. Olsen Group and is managed by Natural Power, another member of the Fred Olsen group. Turbine maintenance and service is carried out by technicians from Nordex SE and Siemens. Since the completion of Crystal Rig 2 in 2010, Siemens have based their main service centre for all wind farms in the South East with Siemens turbines in use at the turbine control centre at Crystal Rig whose offices are shared with Natural Power. This enables Siemens technicians with easy access to all 60 turbines on site and to the nearby wind farms of Aikengall 2, Carcant, Toddleburn and Black Hill wind farms. Nordex base their service centre in Loanhead which is based half way between Crystal Rig 1/1A and Bowbeat Wind Farm where 24 Nordex N60 Turbines fall on the Moorfoot Hills. The farm was built in four stages:- Crystal Rig: Completed in May 2004 it consists of 20 Nordex N80 turbines producing a maximum of 50 MW. Crystal Rig 1a: An extension completed in May 2007 adding a further 5 N80 turbines to increase the maximum to 62.5 MW. Crystal Rig 2 & 2a: Both completed in September 2010〔(RenewablesUK Press Release 23 September 2010 )〕 they consist of 60 Siemens SWT-2.3 turbines in total capable of producing 138 MW. The whole site therefore has 85 turbines and a nameplate capacity of 200.5 MW. Crystal Rig 1 and 1a are connected to the National Grid utility at the Dunbar substation 10 km to the north.〔http://www.fredolsen-renewables.com/?aid=9074435〕 A dedicated substation has been built on site for the connection of Crystal Rig 2 and 2a. A third phase has also been assessed for potential development.〔(Fred. Olsen Crystal Rig 3 EIA scoping report )〕 This would extend the farm to the north of Crystal Rig 2a. It could consist of between 9 and 18 turbines and make use of the spare capacity in the grid connection.〔(Berwickshire News article from 1 September 2010 )〕 ==References== 抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)』 ■ウィキペディアで「Crystal Rig Wind Farm」の詳細全文を読む スポンサード リンク
|